|
Overview | Old
and New Waste Water Treatment Plants |
Treatment
Process Stages
Plan
Design Data
Wastewater generated in Napoleon is collected by a
combined collection system on the West and South sides of town and a
separated system in the North, Central, and West sides of town. The
wastewater is transported into the treatment plant through a 35 inch by 45
inch brick combined sewer and a 12 inch force main under the river from the
south side lift station.
The Napoleon Wastewater Plant is a trickling filter plant which includes
phosphorus and grit removal facilities, primary sedimentation,
nitrification, reaeration basin, final settling, chlorination,
dechlorination and sludge disposal.
The
sludge disposal equipment consists of a primary digester, two secondary
digesters, two belt filter presses and a 258,000 gallon sludge lagoon.
Digested sludge is land applied for use as a soil conditioner.
Back to Top
The original plant was constructed in 1958 and was
basically half the size of the current plant which was completed in 1982.
The 1982 plant expansion updated plant equipment and doubled the
plants capacity with the addition of a new barminutor, one primary tank, a
new chlorination tank, with building and a new primary and secondary
digester.
In order to meet new NPDES permit requirements, a $3.8 million expansion and
rehabilitation project was started in the summer of 1997 and finished in
November of 1998. The project increased the hydraulic capacity of the plant
from 6.0 MGD to 7.5 MGD to provide more capacity for wet weather flows.
The rehabilitated plant also provides for ammonia removal and dechlorination
of plant effluent. The project also included the replacement of mechanical
screens with two new traveling screens; the replacement of sludge collection
equipment in the two existing primary tanks; and the addition of a third
final settling tank and sludge pump, reaeration tanks and a blower building.
Facilities for feeding chlorine gas, alum and sodium bisulfate in the
process stream were also added.
In order to cut costs, the rock media trickling filters were increased in
height from 6 foot side walls to 32 foot and converted to biotowers with
plastic media for ammonia removal and aluminum dome covers were also
installed to protect the media.
Back to Top
The treatment process used at the Napoleon Wastewater
Plant consist of the following basic stages:
|
1.
Screening: removes coarse and stringy materials.
2.
Detritor: removes sand and grit.
3.
Primary Settling Tank: removes suspended solids.
4.
Biotowers: BOD removal and nitrification.
5.
Secondary Settling Tanks: removes additional solids and
phosphorus.
6.
Chlorination: Disinfection of the plant effluent.
7.
Dechlorination: Removal of excess chlorine prior to discharge
of effluent.
8.
Sludge Digestion: removes gas and odors and stabilizes
sludge.
9.
Belt Filter Press:
For dewatering of digested sludge.
|
SCREENING
On entering the
plant, the sewage is channeled through one of two traveling screens. The screens remove large solids and trash that could otherwise
interfere with the operation of the plant. At appropriate intervals, the
debris accumulated on the screens is removed for disposal to the sanitary
landfill. The screens are
located in the new screen room at the
northeast corner of the Main Building.
DEGRITOR
Sewage is then pumped to one of the
two grit removal channels in front of the Main Building.
The mechanism is essentially a large mechanical rake, which drags the
grit that settles out in the bottom of the channel, out of the channel and
down the length of the basin and up the sloping end into a storage bin.
The motion of the mechanism washes the grit as it is worked up the
incline. If the grit was not
removed from the sewage at this point, it would finally build up a solid
cake in the bottom of the tanks
and digesters, thus seriously reducing the capacity of the basins and
digesters, making it necessary to clean the units on a frequent basis.
Primary Settling
From the Degritor the sewage passes
through the end of the channels to the Primary Settling Tanks.
In the primary settling tanks, solid particles in the sewage settle
to the bottom and are swept into a sump by the tanks sweeps on the revolving
mechanism. From there they are pumped to the digester by the sludge
pumps in the Main Building. The
sewage enters the settling tank at the center of the tank and flows through
the v-notch weirs at the perimeter of the tank.
The floating material is collected by the surface sweep mechanism and
disposed of. Settled sewage
from the primary tanks then flows into the recirculation chamber were sewage
is continuously pumped to the high rate trickling filters.
The primary treatment stage of wastewater treatment removes 45 to 50
percent of the pollutants in the raw sewage.
Biotowers
After primary treatment wastewater
still contains solid materials either floating on the surface, or dissolved
in the water, or both. Under natural conditions these substances would provide food
for such organisms as fungi, algae and bacteria
that live in a river or lake. In
our biotowers the sewage is distributed over plastic media in the towers
that provide a medium for the growth of certain bacteria which feed on the
dissolved solids in the settled sewage.
The organisms which develop within the towers
provide BOD removal and Nitrification for ammonia nitrogen removal.
This stage of treatment can remove up to 85 to 90 percent of the pollutants
found in the settled sewage.
Aeration Basin
The
aeration basin consists of two
channels which provide aeration detention time of 15 minutes at 2.5 MGD.
The basin also provides additional soluble BOD reduction, provides a
feed point for alum, phosphorus
removal and conditions the floc from the biotowers.
Secondary Settling
The final settling tanks clarify
the effluent from the trickling filters by removing the solids formed by the
biological process of the biotowers. The
effluent from the settling tanks then flows into the chlorine contact
chamber.
Chlorination
In the chlorine contact chamber at
average flow, a 45 minute detention time is provided for sterilization of
harmful bacteria that may have survived the treatment process.
The flow through the tank is in a snake-like flow to maximize the
contact between chlorine and the effluent.
The chlorine is provided from two gas chlorinators, which are
connected to a bank of 150 lb. cylinders.
Dechlorination
Chamber
At
the end of the chlorine contact basin, the chlorinated water flows into a
baffled basin were Sodium Thiosulfate is added, to remove any chlorine still
remaining in the plant effluent. The effluent then flows to the regulation
chamber located to the east of the plant, just outside of the dike and then
through the outfall sewer into the river.
Sludge
Digesters
The
solids that are removed as sludge are pumped to the primary digester where
they are heated and kept in circulation at a temperature of 95 degrees
Fahrenheit.
At this temperature the volatile portion of the sludge is broken down
efficiently by anaerobic bacteria. During
this process methane gas and carbon dioxide are formed, along with the
reduction of the sludge volume. The
secondary digester is equipped with a gas tight floating cover which floats
on a cushion of gas collected above the liquid surface.
The cover holds a normal day's gas production and its weight
regulates the gas pressure. The
gas produced is used to heat the main building and heat the sludge.
The sludge is stored for a time in the secondary digester and as it
stratifies, the remaining liquid is drawn of near the top and is pumped back
to the plant influent. The
digested sludge is then pumped to the Belt Filter Press Building.
Belt Filter Press
The digested sludge is then processed through
the two 1.5 meter belt filter presses. As the sludge flows into the belt
filter press, a polymer is mixed with the sludge to coagulate the solids and
the remaining water is then removed as the sludge continues through the
press. The sludge enters the press at 5 - 6% solids and comes off the press
at 18 - 23% dry solids. After dewatering, the sludge has no objectionable
odor. The sludge is then loaded on trucks and disposed of either as
fertilizer or land filled.
Back to Top
Plan
Design Data
All
Units in Service
|
Average Daily Flow: |
2.6 MGD
|
| Maximum
Daily Flow: |
4.7 MGD |
| Peak
Hydraulic Flow: |
7.5 MGD |
| Influent
BOD at Average Flow: |
4,770 lbs.
|
| Influent
SS at Average Flow: |
4,987 lbs.
|
| Influent
Phosphorus at Average Flow: |
163 lbs.
|
|
Primary Tanks
:
|
•
2
-@ 45 ft. diameter, with 8.5 ft. water depth
• 13,512
cf each, 101,070 gal. each or 202,140 gal. for both tanks
• 141.3
linear feet of weir per tank
|
| Biotowers:
|
•
2
- @ 55 ft. diameter, 30 ft. depth of media
• 268,488
sf and 142,560 cf of media (71,239 cf per filter)
• 297
blocks of media per layer, with 30 layers per filter
|
| Aeration Basin:
|
•
30
ft. x 6 ft. x 9.5 ft. = 1710 cf
• 1710
cf x 7.48 gal/cf = 12,791 gal. x 2 = 25,582 gal. total
|
| Final Tanks:
|
•
3
- @ 60 ft. diameter, 12 ft. water depth
• old
final tanks - 2 @ 33,912 cf. 253,789
gal./each
• new
final tank - 1 @ 33,912 cf. 253,662 gal.
• 188
linear feet of weir per tank
• 761,240
gal. Total Final Settling
|
| Chlorine Contact Basin:
|
•
1
- basin 32 ft. x 39 ft. divide into 2 chambers
• 15
minute detention time @ 7.5 MGD
• 45
minute detention time @ 2.5 MGD
|
|
Primary Digester:
|
•
55
ft. diameter, 20 ft. water depth
• 47,500
cf and 355,250 gal. capacity
|
| Secondary Digester:
|
•
55
ft. diameter, 20 ft. water depth
• 55,755
cf and 417,056 gal. capacity
|
| Belt
Filter Building: |
• 2 - 1.5 Meter Presses
• 280 - 350 lbs. dry solids/hr.
• 70 ft. x 140 ft. sludge storage area
|
| Sludge Lagoon:
|
257,700
gal.
|
|
Emergency Power:
|
1275
KW Generator with automatic transfer switch
|
Back to Top
|